By Sierra Lauder, Director of Events and Downtown Development, Tillamook Area Chamber of Commerce
This is the week! Monday, April 9th will be the pivotal day in transitioning in to the next phase of the project. Regardless of the weather, re-striping will take place, freshening up arrows and realigning the traffic pattern on Main Street. North of the bridge, the small buffer area between north and southbound traffic that has been utilized as a turning pocket for Rosenberg’s will disappear, and access in to Rosenberg’s may shift from their north driveway entrance to their south driveway entrance as road work north of the bridge begins in earnest.
South of the bridge to First Street, what happens on Monday will depend on the weather. The stretch of the road that runs from the southern end of the new bridge to First Street that has been stripped down and regraded is set to be repaved. However, asphalt requires certain temperatures and climate conditions, and with the ever evolving forecast it is too volatile to be sure that paving can occur Monday. If it doesn’t work out for Monday, getting that paving in and complete will be the top priority as soon as weather allows.
Main Avenue in the downtown, from First to Fourth, will see a dramatic change. Regardless of weather, the gap between the new curb and gutter and the road base along the east side of Main will be filled, and then the new striping will shift the traffic all the way to the east side of Main along the newly completed sidewalk there. Parking on both sides of the street between First and Fourth will remain closed, and construction on the west side of Main will begin.



Stay safe out there.
For more FAQ’s about our project, including conceptual drawings that help visualize the project in its entirety, you can check out the ODOT page: www.TillamookTraffic.org