What to expect this week:
– Building slab vapor barrier installation.
– Building slab rebar installation.
– Building slab concrete pour scheduled for Friday 11/22.
Major milestones on the project:
– Perimeter stem walls have been poured, waterproofed, insulated and backfilled.
– Building slab subgrade has been compacted and fine graded.
– Interior under-slab plumbing and electrical rough-in is complete.
About the new Health Center and Pharmacy:
– The Health Center and Pharmacy project is being developed by the Nehalem Bay Health District. The District will own the facility and medical service will be provided by the local non-profit Nehalem Bay Health Center.
– The new Health Center will triple the size of the current facility (the former Rinehart Clinic) and have space to accommodate specialty services, including dental and x-ray.
– Substantial funding for the project has been provided by a local bond measure – thank you to the community – and generous contributions from among others 1st Security Bank of Washington, and the Roundhouse, Samuel S. Johnson, Ford Family and Autzen Foundations.